Key dates:
• March 24, 2025 — Start reconstruction Block 1 (Colorado Avenue to Pikes Peak Avenue)
• Early July 2025 — Complete Block 1; start Block 2 (Pikes Peak Avenue to Kiowa Street)
• September 2025 — Complete Block 2; start reconstruction of Historic Busy Corner
• Late 2025 — Final pavement overlay for Tejon Street